ISO 9001 · 14001 · 45001 certified · EGPC-registered
ENGINEERINGPRODUCTION ENGINEERING

Integrated production modelling

A complete integrated model of your production system, built, calibrated, optimized and handed over with your engineers trained to run it.

Platform
Petroleum Experts IPM
Suite
PROSPER, MBAL, GAP, RESOLVE, PVTP
Models
Well, reservoir and network, coupled
Hand-over
Models, scripts, trained engineers

APPLICATIONS

Where it is applied

  • Field-wide optimisationWells, network and facility in one model
  • Gas-lift allocationThe gas sent where it earns the most oil
  • DebottleneckingThe constraint that limits the field
  • Development planningNew wells and compression tested in the model first
  • Back-pressure effectsTie-ins and routing changes
  • ForecastingProduction forecasts that honour the network

HOW THE STUDY RUNS

Frame, build, optimize, hand over

1 · FRAMING AND DATA

Framing and data analysis

Opportunity framing with your team and full data analysis, closed with an inception report so scope, assumptions and data are agreed before modelling.

2 · BUILD

Model build and calibration

Well, reservoir and network models coupled on Petroleum Experts IPM (PROSPER, MBAL, GAP, RESOLVE, PVTP) and calibrated to an agreed base case.

3 · OPTIMIZE

Multi-scenario optimization

Bottlenecks identified at each step; gas-lift and choke settings optimized system-wide; options compared on production and economics.

4 · HAND OVER

Assurance, hand-over and training

Every case reviewed with your stakeholders, a completion report, and on-job training for your engineers on the handed-over models; OpenServer automation scripts stay with you.

CASE STUDY · ANONYMIZED

IPM build with capability transfer

Offshore gas-condensate operator

SCOPE

One calibrated model of the production system, and a client team able to keep it.

DELIVERED

PROSPER/GAP/MBAL suite built and matched; multi-scenario optimization across operating envelopes; OpenServer reporting automation; five client engineers trained on-job through hand-over.

  • ±15% match achieved
  • System-wide optimization live
  • 5 engineers trained on-job

PRODUCTION ENHANCEMENT AND EVALUATIONS

From screening to execution

A defined process for improving existing wells and finding bypassed opportunity: the most cost-effective barrels on a declining asset.

  1. 1Collect and screen data. Data analyses, wellbore utilization and material-balance screening across large well populations.
  2. 2Identify gaps and prioritize. Log analysis, flow evaluation, well-test interpretation, decline analysis and nodal modelling isolate the gap per well.
  3. 3Recommend and design. Per candidate: re-perforate, acidize, fracture, install or modify artificial lift, infill or lateral drilling.
  4. 4Execute and evaluate. Post-treatment evaluation against forecast; economics confirmed; screening model updated.

CASE STUDY · ANONYMIZED

Field-wide production enhancement screening

Mature-field operator

SCOPE

Offset decline without new wells: find, rank and design the interventions hiding in an existing well stock.

DELIVERED

Screening across the full stock; production-gap diagnosis per candidate (logs, tests, declines, nodal); designs for re-perforation, acid and lift changes ranked by uplift and economics; a post-treatment evaluation loop.

  • Full stock screened
  • Ranked intervention inventory
  • Post-job evaluation loop

WHERE IT FITS

Frame, build, optimize, hand over

  1. FRAMEAn inception report agrees scope, assumptions and data first
  2. BUILDWell, reservoir and network models coupled and calibrated to a base case
  3. OPTIMIZEGas-lift and choke settings set system-wide, options compared on economics
  4. HAND OVERModels, OpenServer scripts and on-job training stay with you

WHY IT PAYS · PUBLISHED SOURCES

Network models find the gas that pays

+510 bopd

From an integrated PROSPER/GAP network model on a GUPCO offshore field: gas reallocated, and about 5.5 MMscfd of HP gas saved and sent to three shut-in wells.

GUPCO · OTC-24703-MS

+19.43%

Oil from a PROSPER model of a water-oil jet pump on an offshore well, with tubing roughness shown to cost 20–25% of liquids.

PetroGulf Misr · Petroleum Research, 2023

Published case histories · Egypt first

Results reported by operators and vendors in the sources listed below. They are third-party results, not Streamlines' own.

Published case histories
Where · whenWhat was donePublished resultSource
Egypt · offshore Field A, GUPCO · 2014Integrated PROSPER/GAP network model; gas reallocated and saved gas sent to three shut-in wells+510 bopd in total; ~5.5 MMscfd HP gas savedOTC-24703-MS
Egypt · offshore well GA-1A, PetroGulf Misr · 2023PROSPER model of a water-oil jet pump; motive rate and pressure optimisedOil +19.43%; tubing roughness shown to cost 20–25% of liquidsPetroleum Research 8(4)

Name one system and one bottleneck.

The CISS team replies with a scope, the data we would need and the acceptance criteria.

Discuss a modelling study