Case study · anonymized
Commissioning & ramp-up of a debottlenecked train
Onshore processing operator
The question
Bring a modified train online without sacrificing the base production that paid for it.
What we delivered
Systems-completion verification; procedures rewritten against the updated model; guarantee test designed and witnessed; ramp-up choke schedule with live deferral accounting — plateau reached ahead of plan with the base protected.
Outcomes
- Guarantee test passed & witnessed
- Base production protected
- Plateau ahead of schedule